Think Critically, No. 1 | Bias: the planning fallacy | Case: California High-Speed Rail
The first price on a big public project is usually the best-case story of that one project. The track record of similar projects is a far better guide.
In November 2008, California voters approved Proposition 1A, a $9.95 billion bond to help build a high-speed train between San Francisco and Los Angeles. The pitch was concrete. The first phase, linking the Bay Area to Los Angeles and Anaheim, would cost about $33 billion, with trains running by 2020 (Bailey, 2008). Federal, local, and private sources were expected to cover roughly $24 billion of that, but none of it had been committed when people voted (Skelton, 2008).
It is now late 2026, and no passenger has ridden the line. The Authority’s 2026 Business Plan puts a slimmed-down, “optimized” Phase 1 at about $126.1 billion, and re-estimates the full Phase 1 scope at about $231.3 billion (California High-Speed Rail Authority [CHSRA], 2026a). Through February 2026, the program had spent about $15.0 billion, most of it on the Central Valley stretch between Merced and Bakersfield (CHSRA, 2026b). In July 2025, the Federal Railroad Administration terminated about $4 billion in federal grants, concluding the Authority could not deliver that first segment by its 2033 deadline (Federal Railroad Administration [FRA], 2025).
First, do not fall for the scary multiple
The fast reaction is “$33 billion became $231 billion, a sevenfold blowout.” That headline is itself a trap. The 2008 figure was in 2008 dollars. Adjusted with the Consumer Price Index, $33 billion in 2008 is roughly $49 billion in 2025 dollars (U.S. Bureau of Labor Statistics, 2026; calculation by PolicyBombs). The newer estimates are in year-of-expenditure dollars, which bake in future inflation, and the scope has shifted, including plans to share existing tracks in some places.
So there is no clean ratio. But there is also no honest conversion that turns $126 billion into $49 billion, and the opening date has slid by more than a decade. The overrun is real. It just needs to be measured correctly.
What the planning fallacy is
Daniel Kahneman and Amos Tversky gave this pattern its name. People forecast a project from the inside, by imagining how this particular plan will unfold, and they neglect the outside view: how similar projects actually turned out (Kahneman & Tversky, 1979).
It shows up at every scale. In one classic study, psychology students predicted they would finish their honors theses in about 34 days on average. They took about 56, and fewer than a third finished by the date they had predicted (Buehler et al., 1994).
Megaprojects show the same tilt. In a study of 258 transportation projects across 20 countries, measured in fixed prices, costs were underestimated in 86% of cases. Actual costs averaged about 28% above estimates, and rail projects averaged 44.7% (Flyvbjerg et al., 2002).
In System 1 terms, the fast mind builds a vivid, coherent plan and feels confident because the story hangs together. System 2, the slower and more deliberate mode, has to do the boring work: find the reference class and ask what usually happens.
An honest caveat. Flyvbjerg and colleagues argue that the cost pattern is best explained by strategic misrepresentation, meaning promoters lowball to win approval, not only by innocent optimism. That is their interpretation of the evidence, and a reasonable one, but it is an interpretation. The careful reading holds both channels: lazy inside-view forecasting and incentives to lowball. The planning-fallacy pattern itself rests on decades of field data on real projects, not on one fragile lab trick.
How the first number gets used on you
- The down-payment pitch. A ballot measure leads with the bond amount, not the full cost. Voters hear “$9.95 billion” and the rest of the funding gap fades into the background.
- “On time and on budget.” Stadiums, transit lines, government IT systems, and Olympic bids are sold with a single confident date and price. The base rate for those promises rarely appears in the brochure.
- The contractor’s low bid. At home, a renovation quote wins the job, then change orders arrive. The incentive is the same as in public works: the low number gets the yes.
- “It only costs each taxpayer $X.” Dividing a first estimate by population makes a forecast sound like a receipt.
- The opposing trick. Critics can exploit the same bias in reverse by comparing 2008 dollars to future dollars to manufacture the most shocking multiple. A misleading number does not become honest because it points at a real failure.
Deception check: five questions for the next big price tag
- Whose dollars? Is the cost in a base year’s dollars, today’s dollars, or year-of-expenditure dollars? Never compare across them without adjusting.
- What is the reference class? Ask how comparable projects did, not how this one is planned to go. If no one can name a reference class, the forecast is a hope.
- Down payment or full cost? Separate what is being approved today from what the whole thing will cost, and ask who is committed to paying the rest.
- How confident is the estimate? Serious estimates state a confidence level. California’s current figures are stated at a 65% confidence level, meaning roughly a one-in-three chance of coming in higher (CHSRA, 2026b). If no confidence level is given, ask why.
- Who built the number, and what did they want? A promoter seeking approval and an auditor reviewing a finished project face very different incentives.
The lesson
The planning fallacy is not an argument against building things. Ambitious projects have value, and some succeed. It is an argument for pricing them honestly at the moment of decision, using the record of similar projects instead of the best-case story of this one. The time for slow thinking is before the vote, when the first number is still a wish.
References
Bailey, E. (2008, October 15). Backers hope voters give bullet train a shot. Los Angeles Times. https://www.latimes.com/archives/la-xpm-2008-oct-15-me-fasttrain15-story.html
Buehler, R., Griffin, D., & Ross, M. (1994). Exploring the “planning fallacy”: Why people underestimate their task completion times. Journal of Personality and Social Psychology, 67(3), 366-381. https://doi.org/10.1037/0022-3514.67.3.366
California High-Speed Rail Authority. (2026a). 2026 business plan. https://hsr.ca.gov/wp-content/uploads/2026/06/2026-Final-Business-Plan-060126-A11Y.pdf
California High-Speed Rail Authority. (2026b). 2026 business plan technical supporting document: Capital cost basis of estimate report. https://hsr.ca.gov/wp-content/uploads/2026/06/2026-Business-Plan-Basis-of-Estimate-A11Y.pdf
Federal Railroad Administration. (2025, July 16). Letter from Acting Administrator Feeley to Ian Choudri, California High-Speed Rail Authority. U.S. Department of Transportation. https://railroads.dot.gov/sites/fra.dot.gov/files/2025-07/FRA%20Acting%20Administrator%20Feeley%20Letter%20to%20Mr.%20Ian%20Choudri%207.16.25.pdf
Flyvbjerg, B., Holm, M. S., & Buhl, S. (2002). Underestimating costs in public works projects: Error or lie? Journal of the American Planning Association, 68(3), 279-295. https://doi.org/10.1080/01944360208976273
Kahneman, D., & Tversky, A. (1979). Intuitive prediction: Biases and corrective procedures. TIMS Studies in Management Science, 12, 313-327. https://archive.org/details/DTIC_ADA047747
Skelton, G. (2008, October 27). Timing is not so swift. Los Angeles Times. https://www.latimes.com/archives/la-xpm-2008-oct-27-me-cap27-story.html
U.S. Bureau of Labor Statistics. (2026). Consumer Price Index for All Urban Consumers (CPI-U), U.S. city average, all items (CUUR0000SA0) [Data set]. https://data.bls.gov/timeseries/CUUR0000SA0
Weekly email
Get the weekly PolicyBomb.
One grade a week. One number. The sources. No party line.
Unsubscribe any time. We do not sell the list.